Park and Ride Project – Construction Update #3

  • Revised1Monday, 3/24 through Friday, 3/28: The Contractor will continue excavation and installation for sanitary and water main utilities, crossing Jonathan Carver Parkway (CSAH 11) at Ironwood Drive.
  • Friday, 3/21 through Sunday, 3/23: Ironwood Drive will be open to weekend traffic. 
  • Monday, 3/24: Ironwood Drive, from Jonathan Carver Parkway (CSAH 11) to Basswood Court, will be closed during the connection of new sewer and water main. This closure will last approximately two to three weeks. Local traffic should use White Pine Way for access to residential streets.