2019 Improvement Project

Weekly Update: September 16, 2019

Click HERE for the project staging map.

Construction Update
Anticipated work for this week:

  • Elm Drive: restoration grading is scheduled to occur towards the end of this week, weather permitting.
  • Diedrich Drive & Kirche Hill Drive: restoration grading is anticipated to occur towards the end of this week, weather permitting.
  • Sunny Ridge Drive & Lylewood Parkway: street excavation is scheduled to continue throughout this week.

Traffic Alerts
Lylewood Parkway will be closed for approximately 4 days to complete scheduled street work. This localized closure will be north of the intersection of 6th Street and Lylewood Parkway. This closure will take place during the week of September 16th beginning Monday (9/16). Local access to property owners on Sunny Ridge Drive will be maintained. Please see below for an alternate route.

 

Overview
The Carver 2019 Improvement Project consists of improving four areas of the community.  Click HERE to view the project staging map.

Diedrich Drive and Kirche Hill Drive:
New sanitary sewer and watermain system for residents to connect to

  • New storm sewer system
  • New concrete curb and gutter and pavement
  • New sidewalk connection along the south side of Kirche Hill Drive to 4th Street

Sunny Ridge Drive, Lylewood Parkway, Elm Drive:

  • New storm sewer system
  • New concrete curb and gutter, pavement, and signage
  • Watermain individual service line improvements on Sunny Ridge Drive and Elm Drive

The alley improvements between 3rd and 4th Street from Broadway Street to the levee:

  • New alley and shoulder pavement

Spring Creek Drive:

  • New trail connection on south side of Spring Creek Drive from the new Meadows at Spring Creek development to Mount Hope Road

Project Timeline

Project Updates

Email Updates
To sign up for project updates, please enter your contact information below.

 

 

 

Newsletters

May 8, 2019 – Preconstruction Newsletter

Preconstruction Documents

Project Update/Open House Notification – January 31, 2019 – Diedrich Drive, Kirche Hill Drive

Project Update/Open House Notification – January 31, 2019 – Elm Drive, Sunny Ridge Drive, Alley

Project Update – December 15, 2018

Resident Guide:  Kirche Hill Drive and Diedrich Drive Improvements 

Resident Guide:  Elm Drive and Sunny Ridge Drive Improvements 

Resident Guide:  Downtown Alley Improvements 

2019 Project Feasibility Study

Project Contact

Josh Eckstein, Project Engineer (Bolton and Menk)

952-448-8838

josh.eckstein@bolton-menk.com