2019 Improvement Project

Page Updated July 19, 2019

Weekly Update: July 19, 2019

Click HERE for the project staging map.

Construction activities are scheduled to begin in the Elm Drive area on Monday, July 22. Work in this area will last about 4 to 6 weeks.

Traffic Alerts
Elm Drive will be closed while construction activities are taking place. The closure is expected to last about 4 to 6 weeks. Access will be maintained to properties adjacent to the project during non-working hours. There will be times during the project in which access will be temporarily restricted due to construction activities. Residents are suggested to have vehicles parked on side streets off of Elm Drive on workdays prior to 7am to avoid access inconveniences. Please see below for the closure area.

Garbage Collection and Sprinkler System
Please have garbage cans out at the end of your driveway early on pickup days. The contractor will move your trash cans to facilitate garbage pickup if necessary. Temporary house number labels will be placed on the cans to ensure residents receive their trash cans back after garbage pickup. Please do not remove these labels until construction is complete.

If you have sprinkler heads or underground fencing near the roadway, please contact Michael Jabs at 612-269-9970 or Michael.Jabs@bolton-menk.com

Temporary Mailboxes
The contractor will be temporarily removing your mailbox and installing temporary mailboxes at the intersection of Elm Drive and 4th Street West (see map below). Mail will be directed to the temporary mailboxes beginning Monday, July 22. Once construction is completed the contractor will re-install original mailboxes.

 

Overview

The Carver 2019 Improvement Project consists of improving four areas of the community.  Click HERE to view the project staging map.

Diedrich Drive and Kirche Hill Drive:

  • New sanitary sewer and watermain system for residents to connect to
  • New storm sewer system
  • New concrete curb and gutter and pavement
  • New sidewalk connection along the south side of Kirche Hill Drive to 4th Street

Sunny Ridge Drive, Lylewood Parkway, Elm Drive:

  • New storm sewer system
  • New concrete curb and gutter, pavement, and signage
  • Watermain individual service line improvements on Sunny Ridge Drive and Elm Drive

The alley improvements between 3rd and 4th Street from Broadway Street to the levee:

  • New alley and shoulder pavement

Spring Creek Drive:

  • New trail connection on south side of Spring Creek Drive from the new Meadows at Spring Creek development to Mount Hope Road

Project Timeline

Project Updates

Email Updates
To sign up for project updates, please enter your contact information below.

 

 

 

Newsletters

May 8, 2019 – Preconstruction Newsletter

Preconstruction Documents

Project Update/Open House Notification – January 31, 2019 – Diedrich Drive, Kirche Hill Drive

Project Update/Open House Notification – January 31, 2019 – Elm Drive, Sunny Ridge Drive, Alley

Project Update – December 15, 2018

Resident Guide:  Kirche Hill Drive and Diedrich Drive Improvements 

Resident Guide:  Elm Drive and Sunny Ridge Drive Improvements 

Resident Guide:  Downtown Alley Improvements 

2019 Project Feasibility Study

Project Contact

Josh Eckstein, Project Engineer (Bolton and Menk)

952-448-8838