2019 Improvement Project

Updated May 15, 2019

Overview

The Carver 2019 Improvement Project consists of improving four areas of the community.  Click HERE to view the project staging map.

Diedrich Drive and Kirche Hill Drive:

  • New sanitary sewer and watermain system for residents to connect to
  • New storm sewer system
  • New concrete curb and gutter and pavement
  • New sidewalk connection along the south side of Kirche Hill Drive to 4th Street

Sunny Ridge Drive, Lylewood Parkway, Elm Drive:

  • New storm sewer system
  • New concrete curb and gutter, pavement, and signage
  • Watermain individual service line improvements on Sunny Ridge Drive and Elm Drive

The alley improvements between 3rd and 4th Street from Broadway Street to the levee:

  • New alley and shoulder pavement

Spring Creek Drive:

  • New trail connection on south side of Spring Creek Drive from the new Meadows at Spring Creek development to Mount Hope Road

Project Timeline

Project Updates

Email Updates
To sign up for project updates, please enter your contact information below.

 

 

Weekly Updates

May 15, 2019 – Private utility relocation work is anticipated to begin the week of May 20 for the Kirche / Diedrich Drive areas. Roads will not be closed and access will not be impacted by this work. The primary City contractor—Wm. Mueller and Sons—is scheduled to begin work in the Kirche Hill Drive and Diedrich Drive area the first week of June. Kirche Hill Drive and Diedrich Drive will be closed to through traffic at that time, but access will still be maintained for residents travelling to their homes.

Newsletters

May 8, 2019 – Preconstruction Newsletter

Preconstruction Documents

Project Update/Open House Notification – January 31, 2019 – Diedrich Drive, Kirche Hill Drive

Project Update/Open House Notification – January 31, 2019 – Elm Drive, Sunny Ridge Drive, Alley

Project Update – December 15, 2018

Resident Guide:  Kirche Hill Drive and Diedrich Drive Improvements 

Resident Guide:  Elm Drive and Sunny Ridge Drive Improvements 

Resident Guide:  Downtown Alley Improvements 

2019 Project Feasibility Study

Project Contact

Josh Eckstein, Project Engineer (Bolton and Menk)

952-448-8838

josh.eckstein@bolton-menk.com