March 17, 2023
Timber Creek continues to be an active construction site. In total, the site will include 348 new residential units with a mix of both single family and townhome units. Three phases are fully through the City development process with additional phases anticipated in coming months.
Prior to the Preliminary Plat process, a concept for the project moved through both Planning Commission and City Council and an Environmental Assessment Worksheet (EAW) was required due to the number of units. The Timber Creek Environmental Assessment Worksheet (PDF) is available for review.
Previous planning steps have included review of a concept plan submitted by Summergate. The sketch plat is a basic design of what a project could look like prior to in-depth engineering of the site.
A full sized Approved - Song Concept is available for review.
The Planning Commission reviewed the sketch plat at the May 16, 2019 meeting. The City Council reviewed the information at the June 3, 2019 meeting.
Check back to this page often to keep up with the project as it progresses.