- Home
- Projects
- City Projects
- 6th Street West Improvements
6th Street West Improvements
Construction Update: April 2023
The 6th Street Improvements Project is scheduled to resume the week of May 1, 2023, weather dependent. Construction will take place from Broadway Street to Jonathan Carver Parkway, while crews work to complete the remaining improvements associated with this project. Some of the remaining work includes, but is not limited to:
- Driveway paving
- Sidewalk construction
- Ditchway grading
- Final lift of asphalt paving
Sixth Street will remain open to the public during this work, however, please use extreme caution when traveling through the work zone. Work is anticipated to continue through the end of May or into early June.
Project updates can be found in the 6th Street West Construction Updates section on this page.
What is being built?
Improvements include rebuilding the roadway, improving the storm sewer network, and upgrading the pedestrian facilities along the corridor. Other updates will be made at this time to enhance the functional uses, safety and visual quality of the corridor, such as striped bike lanes, additional lighting and adjustments to key intersections.
Other improvements being made by the city with this rehabilitation effort are intended to enhance the functional uses, safety, and visual quality of the corridor including the following:
- Striped bike lanes to enhance the non-motorized uses of the primary corridor into downtown Carver
- Additional lighting for safety and security
- Adjustment to key intersections for operational and safety improvements
Project history
The City of Carver was successful in a competitive grant pursuit and received $1.25 million in State Funding to reconstruct 6th Street West from Jonathan Carver Parkway to Broadway Street. This roadway serves as a primary route between Downtown Carver and Highway 212 and provides access to many key destinations, such as Carver Fire Department and the city’s largest community park.
In addition to the deteriorating pavement in need of repair, this roadway consistently floods, causing:
- rapid deterioration of the roadway
- dangerous icy conditions during winter months
- flooding of adjacent properties
- temporary road closures during heavy storms
Public Involvement
Public engagement has occurred with directly impacted residents along the corridor, with additional information releases planned to update the community on the project details as they are further defined and prior to construction.
Project Documents
Corridor Layout:
Broadway and 6th Street:
Lylewood Parkway and 6th Street:
East of Lylewood looking West:
-
November 25
Construction updates for the 6th Street West Project -
November 18
Construction updates for the 6th Street West Project -
November 11
Construction updates for the 6th Street West Project
Phase: Completed
(minor work to be done in spring 2023)
Schedule: Construction began in July, and the road re-opened to traffic in November. Minor work to be completed in Spring 2023.
Location: 6th Street West from Jonathan Carver Parkway to Broadway Street
-
Nicole Krause
Senior Project Communications SpecialistPhone: 612-269-9970