Construction Update: September 9, 2022
Work completed the week of September 5:
This week, the storm sewer utility construction continued throughout the corridor. Comcast crews were onsite to commission the recently installed utilities. Finally, grading improvements were completed to the drainage ditch that runs parallel to 6th Street West.
Work planned the week of September 12:
Work will include:
- Watermain construction with deep excavation within the street will begin on Monday.
- Street work will continue.